At the Lakeway Activity Center, the playscape built by Noble General Contractors and Play & Park Structures has been open since September 2025. In its October 19 update to City Council, the city wrote that it has "quickly become a popular destination for Lakeway families and visitors" and noted it had been named one of the "Top 7 Playscapes in the Greater Austin Area." Of the five projects in the $22 million parks bond that Lakeway voters approved in May 2024, it is the only one finished. It was also the cheapest.
About $10 million and several years separate that playscape from the bond's largest project. The order matters to anyone who uses these parks. The small projects went first and moved quickly. The large ones are where the open questions sit, including how many pickleball courts get built, what the skate and bike park looks like, and how the Swim Center, which hosts classes year-round, gets improved. Residents still have a say in those questions.
Where the $22 Million Stands
In April 2024, ahead of the May 4 election, Community Impact published the city's per-project cost estimates. Set those 2024 numbers beside the status in the October 19, 2026 staff report and the pattern is plain.
| Project | 2024 estimate | Status as of October 2026 |
|---|---|---|
| Lakeway Activity Center playscape | $508,771 | Completed September 2025 |
| Butler Rough Hollow Park | $1,992,721 | Under construction, opening expected summer 2027 |
| Live Oak Tennis Courts | $2,720,639 | Design not started |
| Lakeway Swim Center | $6,020,532 | Early talks with design firms |
| Lakeway City Park | $10,750,763 | In design, construction projected fall 2027 to summer 2029 |
The two projects you can see, one finished and one rising, add up to about $2.5 million, or roughly 11% of the bond. City Park and the Swim Center together account for about $16.8 million, more than three-quarters of it, and neither has a contractor yet.
Butler Rough Hollow Park Bought Its Equipment Early
Butler Rough Hollow Park is the city's current focus. It is an 11-acre site off Crosswind Drive near Rough Hollow Elementary School. Millis Development & Construction is the contractor, and Pape-Dawson Engineers is overseeing construction. The groundbreaking was in July 2026. According to the Statesman's Lake Travis View, Pape-Dawson engineer Varsha Gudla told council the project is on schedule, with crews installing utilities and pouring concrete.
The final design, as Community Impact described it in March, includes an amphitheater with limestone-block seating, a mountain-bike course, a basketball area with six hoop stations, a multisports field with baseball and soccer equipment, a ninja course, and a playground with accessible and shaded structures. In September, RH Lakeway Development Ltd., the primary developer behind Rough Hollow, donated $50,000 toward the park.
According to the staff report, in November 2025, eight months before groundbreaking, the city bought the park equipment in advance "to avoid anticipated price increases and potential delivery delays." On any build, buying long-lead items early is one of the few real hedges against cost escalation. It only works when the design is settled enough that you know exactly what to order, and that is why the smaller projects have moved first.
On timing, the city's own report says Butler Rough Hollow Park should be finished and open in summer 2027. Community Impact reported a May 2027 completion. Plan around summer.
City Park Holds Half the Bond and Most of the Pressure
Lakeway City Park received the largest allocation in 2024 at $10,750,763, nearly half the bond. It is still in design with the engineering firm Dunaway. The city's report cites the park's topography and its closeness to Lake Travis among the factors that make it a harder site than most.
The plan is broad. Community Impact's October 22 update lists more parking and better connections, an all-wheels park, improved trails, an expanded dog park, and a more accessible play structure to replace the existing Hurst Creek Road playground. An earlier Community Impact piece described the concept plan as having a full vehicle loop, a looped pedestrian trail, a skate park, a pump track, lake overlooks, relocated sand volleyball, and separate areas for large and small dogs. Dunaway project manager Molly Pell told council the design would more than double the park's parking.
The cost picture depends on which outlet you read. Community Impact calls it a $10.6 million improvement project. The Lake Travis View reported that Pell put the construction estimate at $11.4 million against a $9.5 million construction budget, a gap of roughly $1.9 million that Dunaway is working to close. The city's written report gives no figures.
Timing explains part of the pressure. The bond's project estimates went to council on March 4, 2024. City Park is not expected to go out to bid until fall 2027, about three and a half years later. "We are trying to hold these as close to budget as possible," Parks Director Andra Bennett told council, according to the Lake Travis View.
Pickleball Is Where the Gap Shows Up First
When a design runs over budget, the features still being argued about are usually the first to get trimmed, and at City Park the pickleball courts are one of them.
According to the Lake Travis View, the current plan replaces the four pickleball courts in the park's south area and adds two more. Many residents have asked for four new courts, and Bennett said the budget overrun means two additional courts may not fit the final design. Resident John Dallas, who told council he has played at Lakeway's courts for several years, put the case this way in the Lake Travis View's account:
"Pickleball is fun because it's social. The community (is) very engaging. There's a lot of players, and I think we'd have even more if we had more courts."
Resident Larry Harlan told Community Impact that the bond as assembled "included four new pickleball courts in addition to the four that had already been moved." He said players were surprised to hear "zero to two new" courts discussed at the September meeting, and added, "We just want to have an opportunity to engage before a final decision is made."
Skating and biking are in a similar spot. In September 2026, city staff and the design team held a feedback meeting focused only on the proposed skatepark and bike park, to hear from user groups the city said "had not yet been fully represented in previous community discussions." The staff report says the city will keep updating council and "seek additional community input" as plans and cost estimates are refined. No date has been posted yet.
The Swim Center and Tennis Courts Haven't Reached Design Yet
The Lakeway Swim Center has the bond's second-largest allocation at $6,020,532. Staff have started only preliminary discussions with engineering and design firms. Bennett called it the most challenging of the five projects, and the Lake Travis View reported that part of the reason is that the center hosts classes year-round. Renovating a facility while keeping it in use comes down to phasing, and phasing decisions tend to drive both schedule and cost. No timeline has been published.
The Live Oak Tennis Courts, budgeted at $2,720,639 in 2024, have no design work underway. Staff have contacted the United States Tennis Association about possible grants and are reviewing funding options. Outside money has already shown up for the bond's other projects. The Lake Travis Rotary Club gave $50,000 to the Activity Center playscape, and RH Lakeway Development gave $50,000 to Butler Rough Hollow Park.
The Calendar From Here to 2029
Based on the October 19 council update and the reporting that followed it, the order of events looks like this:
- Now: The Lakeway Activity Center playscape is open. Butler Rough Hollow Park is under construction off Crosswind Drive.
- By January 2027: Dunaway and the city plan to finish City Park's design phase.
- Summer 2027: Butler Rough Hollow Park is expected to open to the public, according to the city.
- Fall 2027: City Park is expected to go out to bid, with construction starting the same season.
- Summer 2029: City Park construction is projected to wrap up.
The Swim Center and Live Oak Tennis Courts are not on this list because the city has not yet given them dates.
For a builder, the period between design and bid is when scope gets settled, and City Park's runs from now through January. The city has said it will seek additional community input as City Park's plans and cost estimates are refined. If you're weighing how projects like Butler Rough Hollow Park and the future City Park fit into your own plans in Lakeway, Casey Marquez is happy to talk through what's being built and when. Let's Connect.